Contractor management (UK): a guide for site owners and FM teams
Last updated 16 November 2026 · Sources last checked 16 November 2026
If contractors work in your buildings, you share responsibility for their safety and for the safety of your staff and visitors while they are there. HSE sets out contractor management in five stages: plan the work, choose a competent contractor, control the work on site, keep a check, and review. This page covers what the law asks of you as the site owner or client, what to check before you approve a contractor, and how to control each job.
What the law asks of a site owner
- Your own operations. Every employer must conduct their undertaking so that people who are not their employees, contractors included, are not exposed to risks to their health or safety, so far as is reasonably practicable (Health and Safety at Work etc. Act 1974, section 3).
- Shared workplaces. Where two or more employers share a workplace, even for a few hours, each must co-operate with the others, co-ordinate their safety measures, and tell the others about risks from their own work (Management Regulations 1999, regulation 11).
- Information for visiting workers. A host employer must give the contractor's employer understandable information about the risks to their workers from the host's operations and the measures in place, and must make sure the visiting workers can identify who runs the evacuation procedures (regulation 12). Non-employees working on your premises must get appropriate instructions and understandable information about the risks.
- Construction work. CDM 2015 defines construction work widely: it includes alteration, fitting out, repair, upkeep, redecoration and other maintenance of a structure, and the installation, maintenance, repair or removal of fixed electrical, mechanical, gas and similar services (CDM 2015, regulation 2). So much of the work contractors do in shops, offices and schools is construction work. Where it is, CDM 2015 applies, and as the client you must make suitable arrangements for managing the project and give pre-construction information to designers and contractors as soon as is practicable (CDM 2015, regulation 4). See the construction phase plan guide.
- Asbestos. If you are the dutyholder for a non-domestic building, information about the location and condition of any asbestos must be given to anyone liable to disturb it (Control of Asbestos Regulations 2012, regulation 4). See the asbestos register guide.
HSE's five stages
HSE's guide Managing contractors (HSG159, free to download) sets out five stages (HSE, HSG159). It was written for the chemical industry; HSE says it is useful to other industries too.
- Plan the work. Define the job, identify the hazards and assess the risks, decide the safety conditions, and discuss them with the contractor. Ask for their risk assessment or method statement.
- Choose a contractor. Judge safety competence as well as technical ability. Ask questions, ask for evidence, and share the job and site information. Decide whether subcontracting is acceptable and how you will control it.
- Control the work on site. Contractors sign in and out, have a named site contact, and are briefed on the site rules and hazards before they start. Check the job before work begins, even if they were on site the day before.
- Keep a check. Match the level of supervision to the risk. Check the work against what was agreed, and encourage contractors to report incidents and near misses.
- Review. After the job, look at how it went and how the contractor performed, and record the lessons. Use them when you choose contractors next time.
Before you approve a contractor
HSE says competence is more than qualifications, and the depth of checking should match the risk of the work. A typical approval covers:
| What to check | Why |
|---|---|
| Insurance: employer's liability, public liability, and the cover levels you require | Cover in force, at the level you set, for the dates they will be on site |
| Health and safety policy and arrangements | That they have a working system behind the paperwork |
| Accreditations and trade registrations relevant to the work | Evidence of independent assessment for the trades they will do |
| Operatives' cards and qualifications | The people who arrive are competent for the task, with cards in date |
| Example RAMS from a similar job | How they plan work, and whether their documents are specific to the job |
| Who will supervise, and how they report incidents | Who is in charge on your site, and how you will hear about problems |
| Subcontracting | Who else might turn up, and whether they are checked to the same standard |
Approval is not a one-off. Insurance and cards expire; set a reminder for each expiry and ask for the renewal before it lapses.
Controlling each job
- A work request, not a phone call. Write down the job, the site, the area, the dates and hours, and the permits needed. Send it with the site information the contractor needs: the asbestos register, drawings, isolation points and site rules.
- Documents back before work starts. The contractor's RAMS, and anything else the job needs (COSHH assessments, a lifting plan), written for this job and this site. Check them against the job you described, not just whether they read well. See the RAMS template for what a RAMS should contain.
- Named operatives, inducted. Know who is coming, and make sure each person has done your site induction. See the site induction guide.
- A permit for higher-risk work. Hot work, electrical isolation, confined spaces, roof access. See the permit to work guide.
- Close it out. The contractor confirms the work is finished and the area is safe, and you record it.
Common mistakes
- Approval based on a PDF that has since expired. The insurance certificate on file is last year's.
- A RAMS that was never read. Filed on receipt, with another site's name inside.
- The store manager doesn't know who is coming. The first they hear is when the van arrives.
- Asbestos information not shared. The register is in the office; the contractor is in the ceiling void.
- No review. The same problems with the same contractor, job after job.
How Kompliant Estates handles this
Kompliant Estates is built for this. Contractors onboard themselves through one link: insurance, accreditations, operatives' cards and your policies, with expiry dates read automatically and checked against your minimum cover. You raise a work request with the site's asbestos register, EICR and drawings attached; the contractor sends back their RAMS and who is coming; Kompliant checks the documents against the job you described; each operative does your site induction on their phone; and a named person on your side issues the permit. Kompliant Estates is in early access with a small group of estates and FM teams.
Questions
Am I responsible for a contractor's safety on my premises?
Responsibility is shared. The contractor is responsible for how they do the work. You must run your own operations so that contractors are not put at risk, so far as is reasonably practicable (HSWA section 3), co-operate and co-ordinate where you share the workplace (regulation 11), and give them information about the risks from your premises and operations (regulation 12). If the work is construction work, CDM 2015 gives the client its own duties.
What should I ask a contractor for before they start?
Evidence of insurance at the levels you require, their health and safety arrangements, relevant accreditations or registrations, the cards and qualifications of the people who will attend, and a RAMS for this job. HSE says the depth of checking should match the risk of the work.
Do I need to check the contractor's RAMS?
You should check it fits the job you asked for and your site: the right scope, area, dates and access, the permits you require, and the hazards you know about, such as asbestos. You are not approving how they do their trade, but you are deciding whether to let the work go ahead on your premises.
Does CDM 2015 apply to maintenance work?
Often, yes. The definition of construction work in regulation 2 includes repair, upkeep, redecoration and other maintenance of a structure, and the installation, maintenance, repair or removal of fixed services such as electrical, mechanical and gas systems. Check the definition against the work; where CDM applies, the client has its own duties under regulation 4, and your general duties apply either way.
How often should approved contractors be re-checked?
Whenever something expires (insurance, cards, accreditations) and after each job as part of your review. Many clients also re-approve contractors annually.
Sources
Sources last checked 16 November 2026. This page has not yet been reviewed by an external health and safety adviser.
- Health and Safety at Work etc. Act 1974, section 3
- Management of Health and Safety at Work Regulations 1999, regulation 11
- Management of Health and Safety at Work Regulations 1999, regulation 12
- CDM 2015, regulation 2 (definition of construction work)
- CDM 2015, regulation 4 (client duties)
- Control of Asbestos Regulations 2012, regulation 4
- HSE: HSG159 Managing contractors
This page describes the law in Great Britain (England, Scotland and Wales). Northern Ireland has its own regulations: see HSENI. Kompliant drafts documents for your competent person to review, edit and approve. The guidance on this page is general information, not legal advice.