Method statement example (UK): a worked example, and how to judge one

Last updated 13 November 2026 · Sources last checked 27 October 2026

Below is an example method statement for a small electrical job, produced in Kompliant from a plain-English job description. The company and the job are fictional. After the example you will find a checklist for judging any method statement you come across, and notes on adapting an example to your own work without copying someone else's job into yours.

The example method statement

Example. Fictional company and job.

Replace ceiling LED panels, first-floor open-plan office

Site: Example Client Ltd, first-floor office, Example House, 1 Example Street, Milton Keynes.

Trade: Electrical · Start: 09 Nov 2026 · End: 13 Nov 2026 · Review by: 16 Nov 2026

Before activity commences

  1. Sign in with the site contact on arrival and brief them on the day's zone, access and timing.
  2. Review the 2021 asbestos management survey with the site contact and confirm no asbestos in the first-floor ceiling void, tiles or grid. Stop if anything unexpected is found.
  3. Confirm in writing with the site contact the fire alarm arrangements for any tile holding a detector.
  4. Agree the zone order, staff relocation and walking routes with the site contact.
  5. Check the podium steps, tools, test equipment, PPE, lock-off kit and first aid kit. Confirm the trained first aider.
  6. Barrier off the zone with freestanding barriers and signs and mark the staff walking route. Clear desks from around the work area.
  7. Isolate, lock off, tag and prove dead the zone circuit per Safety-critical element A.

Works methodology

  1. Set up the podium steps under the first fitting, apply the brakes and have the second electrician in position at the foot.
  2. Lift ceiling tiles carefully and slowly, stacking them flat out of walking routes. Do not lift tiles holding smoke detectors unless the fire alarm arrangement is agreed. Do not disturb detectors or emergency lighting.
  3. Disconnect the existing fluorescent fitting from the dead circuit, noting the wiring arrangement.
  4. Lift the fitting out whole with the tubes left in. Wrap it in heavy-duty bag and pass it down. Carry it flat to the skip bag route; never break or remove tubes on site.
  5. Check the ceiling void for damage and for any unexpected material. Stop if found.
  6. Fit the new LED panel per the manufacturer's instructions and make terminations on the dead circuit.
  7. Repeat for each fitting in the zone, moving the podium steps rather than overreaching.
  8. One electrician carries each wrapped fitting to the rear service stairs while the other goes ahead to check the stairs are clear and holds doors. Carry one at a time, waiting if staff are on the stairs. Place fittings in the lined skip bag at the van for recycling as fluorescent waste.
  9. Reinstate ceiling tiles and grid, then vacuum the floor with a HEPA vacuum at the end of each day.
  10. Inspect and test the zone to BS 7671, remove the lock-off, re-energise and check every panel works.
  11. Brief the site contact, remove barriers and release the zone back to staff. Repeat for the next zone.

If a tube breaks: stop, move people away, ventilate for 15 minutes, pick up glass and powder with gloves and damp paper (no vacuum), bag it as fluorescent waste. The lead electrician deals with it.

After activity has been completed

  1. Final HEPA vacuum clean of each zone; remove all packaging and waste.
  2. Confirm all fittings and waste have gone to the licensed carrier for recycling and keep the waste transfer paperwork.
  3. Check all new panels, emergency lighting and detectors are in place and undisturbed.
  4. Complete and issue electrical test results and any certification to the client.
  5. Remove barriers, signs, locks and tags; return the riser cupboard key and confirm it is locked.
  6. Hand over to the site contact and sign out.

Safety-critical element A: electrical isolation, lock-off and proving dead

  1. Agree the zone and its circuit with the site contact. Confirm the other three zones stay live and their staff are unaffected.
  2. Both electricians go to the riser cupboard. Identify the correct zone lighting circuit at the DB from the circuit chart and verify by switching and checking the lights go off in that zone only.
  3. Switch off the circuit and lock it off with the lead electrician's personal padlock. Fit a danger tag showing name, date and contact number.
  4. Lock the riser cupboard on leaving. The key stays with the lead electrician.
  5. At the first fitting, prove dead using an approved two-pole voltage indicator, proved on a known source before and after (prove-test-prove).
  6. Second electrician checks the lock-off at the DB at the start of the zone and again after any breaks, and stays in the zone as spotter and in sight of the lead during work.
  7. No work on live conductors. If a circuit cannot be proved dead, stop and report to the lead electrician.
  8. On completion: inspect and test to BS 7671, remove locks and tags only by the electrician who fitted them, re-energise, check operation and confirm with the site contact.
  1. 1Names the job, site and dates

    “Example Client Ltd, first-floor office… Start: 09 Nov 2026 · End: 13 Nov 2026”

    Swap the site and this would not describe your job.

  2. 2A pre-start condition, in writing

    “Confirm in writing with the site contact the fire alarm arrangements for any tile holding a detector.”

    Work does not start until this is agreed.

  3. 3A stop point

    “Stop if anything unexpected is found.”

    The step tells people when to stop, not just what to do.

  4. 4A control sitting inside a step

    “Lift the fitting out whole with the tubes left in… never break or remove tubes on site.”

    This is the control for the broken-tubes hazard in the risk assessment, written where the work happens.

  5. 5Equipment and number of people named

    “…apply the brakes and have the second electrician in position at the foot.”

    Two people, podium steps, a defined route.

  6. 6It says what happens at the end

    “Confirm all fittings and waste have gone to the licensed carrier for recycling and keep the waste transfer paperwork.”

    Clean-up, waste paperwork and handover are steps, not afterthoughts.

What to check in any method statement

  1. It names the job, the site and the dates. A document that could be about any site has not been written for yours.
  2. The steps are in work order. A list of hazards is the risk assessment. A method statement follows the job from arrival to handover.
  3. The controls sit inside the steps. Where a hazard is controlled by an isolation, a barrier, a permit or a check, the step says so.
  4. It has stop points. At least one place where work must not continue until something is confirmed.
  5. It matches the risk assessment. Every significant hazard has a control that shows up in a step, and every control in a step traces back to a hazard.
  6. It is specific. It names the equipment, the number of people and the access method. Swap the site name and it would no longer make sense.
  7. It says what happens at the end. Clean-up, waste, reinstatement, handover.

Adapting an example to your job

  • Use an example for its structure and level of detail, not its content. Replace everything specific to another job: site, dates, people, quantities, client and equipment.
  • Go step by step and ask whether it is true for your job. Delete what does not apply, and add what the example lacks.
  • Check it against your own risk assessment, not the example's. The method statement should be built from yours.
  • Have your competent person review and approve it before anyone starts work from it.

A note on examples found online

Free examples vary a great deal. Some are generic, some are out of date, and some are written for another country. If you see "SWMS" (safe work method statement), that is usually the Australian term; UK documents use "method statement" or "RAMS" and refer to UK law. Whatever the source, an example is a starting point. The document you use has to describe your job.

For the section-by-section structure, see the method statement template. For the wider RAMS, see the RAMS template.

Draft yours in Kompliant

Describe the job in your own words. Kompliant asks a few questions, then drafts the method statement and the risk assessment together, so the hazards and the steps line up. You edit the draft, approve it, and your team signs by link on their phones. Kompliant produces a draft for your competent person; checking that it fits your job and site is your responsibility.

Already have a RAMS? Get it checked →

Questions

What should a method statement example include?

The job and site details, the sequence of work (before, during, after), the controls at each step, the equipment and number of people, and the emergency arrangements. See the checklist above.

Can I copy an example?

Use it as a guide to structure and level of detail. The content has to be about your job. A document with another firm's site, equipment and sequence in it will not match what you are doing, and the person who approves it is responsible for checking that it does.

Is the example approved for use?

No. It is a draft produced to show what Kompliant generates. Before any method statement is used, someone competent should review and approve it, and the people doing the work should read it.

Where does the risk assessment come in?

The method statement is normally built from the risk assessment (see how they fit together). If you are using an example method statement, write the risk assessment for your job first.