Method statement template (UK): how to write one

Last updated 13 November 2026 · Sources last checked 27 October 2026

A method statement describes, in the order the work will happen, how a job will be done safely. HSE describes it as setting out the logical sequence of the work and the control measures that apply. The structure below suits most trades. Copy it, then fill each part with the details of your job.

What a method statement is for

A method statement turns your risk assessment into instructions people can follow. HSE says method statements are usually produced from risk assessments: they bring together the hazards and control measures identified for a specific job, and they help other contractors understand how your work will affect them (HSE, construction administration).

Is one required? For most work the law does not demand a method statement by name, though HSE notes they are widely used, especially for higher-risk or complex work. Some work has its own written-plan rules: for demolition and dismantling, the arrangements must be recorded in writing before the work begins (CDM 2015, regulation 20). Check the rules that apply to your type of work. A client or main contractor may require one as a condition of the job.

The structure to copy

Before the work starts

  • Who is doing the work, and who is in charge on the day.
  • Site access, permits, parking and induction.
  • Pre-start checks: services identified, isolation arranged, the area made safe, equipment inspected.
  • A briefing for the team, so everyone has read the method statement and the risk assessment it comes from.

How the work is done

  • Numbered steps, in the order they happen.
  • For each step: what is done, by whom, with what equipment, and which control applies.
  • Stop points: places where work pauses until something is checked, for example "do not start until the isolation has been proved".

After the work is finished

  • Clean-up, waste removal and reinstatement.
  • Removing barriers and signs.
  • Handover to the client and sign-out.
  • Anything that needs recording or reporting.

Also include

  • A reference to the risk assessment, so the hazards and controls match.
  • Emergency arrangements: first aid, fire, serious injury, and who to call.

Writing steps that people can follow

  • One action to a step. "Isolate and lock off the supply" and "prove the circuit dead" are two steps, not one.
  • Name the people and equipment. How many people, what access equipment, what tools.
  • Put the control inside the step. If a hazard is controlled by a barrier, a permit or a check, say so in the step where it applies, not only in a table elsewhere.
  • Use stop points. A step that says work must not continue until a check is complete is easier to enforce than a general warning.
  • Say who is responsible. A supervisor, the person leading the task, or the person holding the permit.
  • Avoid "take care". If a step needs care, say what that care consists of.

Keeping it current

The assessment behind it must be reviewed if there is reason to suspect it is no longer valid, or if the work changes significantly (regulation 3(3)). When the method changes, update the method statement and tell the people doing the work. HSE says a method statement can be reused for repeated similar operations, and should be revised when circumstances change markedly.

Method statement or risk assessment?

They are two documents with different jobs. The risk assessment says what could harm someone and what will be done about it. The method statement says how the work is carried out with those controls built in. See how the two fit together.

Draft yours in Kompliant

Kompliant writes the method statement in three named parts: before activity commences, works methodology and after activity has been completed. The works methodology is a numbered sequence with real detail, not one-line fragments. Anything that is dangerous by nature, such as isolating live supplies, working at height or hot work, gets its own safety-critical procedure. It uses your company profile, so the steps reflect how your firm works, and asks you a few questions about the job first. Your competent person reviews and approves the draft.

Already have a RAMS? Get it checked →

Example: works methodology drafted in Kompliant

Example. Fictional company and job.

Job: replace 48 ceiling fittings with LED panels in an occupied first-floor office, two electricians, four zones.

Works methodology

  1. Set up the podium steps under the first fitting, apply the brakes and have the second electrician in position at the foot.
  2. Lift ceiling tiles carefully and slowly, stacking them flat out of walking routes. Do not lift tiles holding smoke detectors unless the fire alarm arrangement is agreed. Do not disturb detectors or emergency lighting.
  3. Disconnect the existing fluorescent fitting from the dead circuit, noting the wiring arrangement.
  4. Lift the fitting out whole with the tubes left in. Wrap it in heavy-duty bag and pass it down. Carry it flat to the skip bag route; never break or remove tubes on site.
  5. Check the ceiling void for damage and for any unexpected material. Stop if found.
  6. Fit the new LED panel per the manufacturer's instructions and make terminations on the dead circuit.
  7. Repeat for each fitting in the zone, moving the podium steps rather than overreaching.
  8. One electrician carries each wrapped fitting to the rear service stairs while the other goes ahead to check the stairs are clear and holds doors. Carry one at a time, waiting if staff are on the stairs. Place fittings in the lined skip bag at the van for recycling as fluorescent waste.
  9. Reinstate ceiling tiles and grid, then vacuum the floor with a HEPA vacuum at the end of each day.
  10. Inspect and test the zone to BS 7671, remove the lock-off, re-energise and check every panel works.

[…]

Safety-critical procedure: electrical isolation

  1. Agree the zone and its circuit with the site contact. Confirm the other three zones stay live and their staff are unaffected.
  2. Both electricians go to the riser cupboard. Identify the correct zone lighting circuit at the DB from the circuit chart and verify by switching and checking the lights go off in that zone only.
  3. Switch off the circuit and lock it off with the lead electrician's personal padlock. Fit a danger tag showing name, date and contact number.
  4. Lock the riser cupboard on leaving. The key stays with the lead electrician.
  5. At the first fitting, prove dead using an approved two-pole voltage indicator, proved on a known source before and after (prove-test-prove).
  6. Second electrician checks the lock-off at the DB at the start of the zone and again after any breaks, and stays in the zone as spotter and in sight of the lead during work.
  7. No work on live conductors. If a circuit cannot be proved dead, stop and report to the lead electrician.
  8. On completion: inspect and test to BS 7671, remove locks and tags only by the electrician who fitted them, re-energise, check operation and confirm with the site contact.

Questions

What is the difference between a method statement and a risk assessment?

A risk assessment identifies hazards and the controls for them. A method statement sets out the sequence of the work and applies those controls step by step. The method statement is normally built from the risk assessment.

Is a method statement a legal requirement?

For most work the law does not require one by name, though HSE notes they are widely used. Some work has its own written-plan rules; for example, for demolition and dismantling the arrangements must be recorded in writing before work begins (CDM 2015, regulation 20). The risk assessment behind it is a legal requirement (regulation 3).

How detailed should it be?

Detailed enough that someone who has not done the job can follow it, and a supervisor can check the work against it. A one-page list of headings is rarely enough for higher-risk work.

Who should read it before work starts?

Everyone doing the work, and anyone whose work it affects. Many firms record this with a signature and date for each person.

Can I use one method statement for several sites?

For repeated similar operations, HSE says a method statement can be reused. Check each site: access, other trades, occupied areas and local rules often differ, and the statement should be revised when circumstances change.

Sources

Sources last checked 27 October 2026. This page has not yet been reviewed by an external health and safety adviser.

This page describes the law in Great Britain (England, Scotland and Wales). Northern Ireland has its own regulations: see HSENI. Kompliant drafts documents for your competent person to review, edit and approve. The guidance on this page is general information, not legal advice.