Construction phase plan template (CDM 2015): who writes it and what to include

Last updated 13 November 2026 · Sources last checked 27 October 2026

A construction phase plan sets out how health and safety will be managed while the construction work is carried out. Under the Construction (Design and Management) Regulations 2015, the principal contractor draws it up when there is more than one contractor on the project, and the contractor draws it up when there is only one. It has to be prepared before the construction site is set up, and kept up to date. HSE says it should be proportionate to the project: for a small job, a simple plan drawn up before work starts is usually enough (HSE, CDM 2015 FAQ).

Who has to write it

  • More than one contractor. The principal contractor must draw up the plan, or arrange for it to be drawn up, during the pre-construction phase and before the construction site is set up (regulation 12(1)). Where more than one contractor is working, or it is reasonably foreseeable that more than one will, the client must appoint a principal designer and a principal contractor in writing, as soon as practicable and before the construction phase begins (regulation 5). If the client does not appoint a principal contractor, the client has to carry out that role's duties.
  • Only one contractor. The contractor must draw up the plan, or arrange for it to be drawn up, as soon as is practicable before setting up the construction site (regulation 15(5)).
  • Domestic clients. CDM 2015 still applies to domestic projects, but the client's duties normally pass to the contractor (one contractor) or the principal contractor (more than one), unless the client agrees in writing with the principal designer to carry them out. If a homeowner does the work themselves, it is DIY and CDM 2015 does not apply (HSE, summary of duties).

What it must cover

The plan must set out the health and safety arrangements for the project and the site rules, taking account of any industrial activity on the site. Where the work includes any of the types listed in Schedule 3, it must also set out the specific measures for that work (regulation 12(2); HSE, planning for construction work). Planning effort should be proportionate to the complexity and risks of the project (HSE, small builders).

A structure to copy

  1. Description of the project. What the work is, the site address, the client, the principal designer (or "not required, one contractor"), the principal contractor, start and planned finish dates, the peak number of workers, whether the project is notifiable to HSE, and existing records and plans (asbestos information, drawings, services).
  2. Management of the work. Who is in charge on site; your health and safety aims for the project; site rules; liaison between contractors and with the client; consulting workers; site induction; how risk assessments and method statements are produced and briefed before each activity; how contractors are selected and controlled; welfare facilities; first aid; fire and emergency arrangements.
  3. Arrangements for controlling significant site risks. A table of risk, where and when it applies, and how it will be controlled. Include only what applies to this project. Typical safety risks: existing services, falls from height, structural stability, demolition, plant and vehicles, traffic routes and deliveries, occupied premises and the public, fire and hot work, confined spaces. Typical health risks: asbestos, silica and wood dust, noise, vibration, hazardous substances, manual handling, lead. Say which RAMS covers each activity in detail.
  4. The health and safety file. The principal designer prepares and updates it, and passes it to the client at the end of the project, or the principal contractor does if there is no principal designer (regulation 12(5) to (10)).
  5. Review and sign-off. The principal contractor must make sure the plan is regularly reviewed, updated and revised so it stays sufficient to manage risks throughout the project (regulation 12(4)). Date it and record who approved it.

Is the project notifiable?

A project must be notified to HSE if the work is scheduled to last more than 30 working days and have more than 20 workers on site at the same time at some point, or if it will exceed 500 person-days. The client notifies in writing, as soon as practicable before the construction phase begins (regulation 6; HSE, how to notify a project (F10)). HSE says to count every day on which construction work is likely, including weekends and holidays.

After the plan is written

The principal contractor must make sure employers and others follow it where required, that a suitable site induction is carried out, and that unauthorised people are kept off the site (regulation 13). Where there is more than one contractor, each must follow the directions of the principal designer or principal contractor and the parts of the plan that relate to its work (regulation 15(3)).

Common mistakes

  • Written after the work has started. The plan has to be prepared before the site is set up.
  • Another project's plan with the names changed.
  • Never updated. Contractors, programme and risks change; the plan has to follow.
  • A manual where a short plan would do. HSE says the plan should be proportionate.
  • "To be confirmed" left on key items when work begins. Gaps are fine in a draft; they should be closed before work starts.

Draft yours in Kompliant

Give Kompliant the project facts you have: client, designer, other contractors, peak number of workers, welfare arrangements and existing records. It drafts the plan under the headings above and keeps it proportionate to the size and risk of the job. Anything you have not given is written as "To be confirmed", so gaps show up before work starts, and it does not invent names, numbers or dates. It flags whether the project looks notifiable, or whether more than one contractor means a principal designer is needed. You review and edit the draft and approve it. Kompliant produces a draft for your competent person to review and adopt.

Example: parts of a construction phase plan drafted in Kompliant

Example. Fictional company and project. Draft, not approved.

Project: refit of a 120 m² ground-floor retail unit, three contractors, a separate principal designer.

The landlord's asbestos register has been requested but not yet received. No strip-out, drilling or disturbance of ceilings, walls or floors may start until it has been received, read and briefed to all trades. The project does not look notifiable to HSE on form F10 (about 20 working days, peak of 8 workers), but this should be confirmed against the programme.

Description of the project (trimmed)

ItemDetail
ProjectRefit of an empty 120 m² ground-floor retail unit, ready for a new tenant. Phases: strip-out of old fittings (week 1); first-fix electrics and shopfit partitions (weeks 1 and 2); second fix and flooring (weeks 3 and 4); testing and handover.
ClientExample Retail Ltd (Property Manager). Named contact: To be confirmed
Principal designerExample Design Studio Ltd (more than one contractor is involved, so a principal designer is required). Named contact: To be confirmed
Principal contractorExample Electrical Ltd […]
Other contractorsExample Shopfitting Ltd (shopfitter); Example Flooring Ltd (flooring)
Start date16 November 2026
Planned finish11 December 2026
Plan review date30 November 2026 (and whenever the work, contractors or risks change)
Peak number of workers8
Notifiable to HSENo (provisional). The work lasts about 20 working days with a peak of 8 workers, below the thresholds of more than 30 working days with more than 20 workers at once, or more than 500 person-days. Recheck if the programme extends.
Existing records and plansAsbestos register held by the landlord (requested, not yet received). As-built drawings from the landlord. Location of existing services: To be confirmed from the drawings and a site survey.

Site risks (3 of 14)

RiskWhere/when it appliesHow it will be controlled
AsbestosStrip-out, drilling, chasing or disturbing ceilings, walls or floors, especially week 1 and any fixing into the fabric. The landlord's register is requested but not yet received.The register must be received, read and briefed to all trades before any work that disturbs the fabric. If it cannot be obtained, work does not proceed until the landlord confirms or a survey is carried out. If suspected material is found, stop, make the area safe, and report to the person in charge, client and landlord. Covered in the strip-out and electrical first-fix RAMS.
Live electrical systemsAll electrical work: first fix, second fix, testing, and any work near existing services.Isolate, lock off with our own lock-off kit and prove dead before work starts. Control and agree isolations with centre management and between trades. Keep the isolation register. Only competent electricians work on installations. Testing and energising are announced to all trades. Covered in the electrical RAMS.
Interface between tradesWeeks 1 to 4, mainly the overlap of first-fix electrics and shopfit partitions (weeks 1 and 2) and second fix and flooring (weeks 3 and 4).The principal contractor sets the sequence, so electrical first fix is complete and tested before partitions are closed in and flooring covers services. Isolations and permits are coordinated through one register. Shared access equipment is booked and controlled. Dust-producing work is separated from finished surfaces. All trades are told before supplies are energised. […]
  1. 1Gaps show as "To be confirmed"

    “Named contact: To be confirmed”

    No invented names. The gap is visible, so it gets closed before work starts.

  2. 2It shows its working on notification

    “Notifiable to HSE: No (provisional)… Recheck if the programme extends.”

    The draft checks the regulation 6 thresholds and says when to look again.

  3. 3An honest gap becomes a stop point

    “If it cannot be obtained, work does not proceed until the landlord confirms or a survey is carried out.”

    The asbestos register has not arrived, so the control is a hold, not an assumption.

Questions

Do I need a construction phase plan for a small job?

On a project covered by CDM 2015, someone has to prepare one: the principal contractor where there is more than one contractor, or the contractor where there is only one. HSE says it should be proportionate, and for a small job a simple plan drawn up before work starts is usually enough.

Who is the principal contractor?

The contractor the client appoints in writing to manage the construction phase, where there is more than one contractor on the project (regulation 5). If the client does not appoint one, the client has to carry out the role's duties.

Is a construction phase plan the same as a RAMS?

No. The plan covers the project: how health and safety is managed across it. A RAMS covers a specific activity. The plan can say which RAMS applies to each activity. See the RAMS template.

When is a project notifiable to HSE?

When the work is scheduled to last more than 30 working days with more than 20 workers on site at the same time at some point, or to exceed 500 person-days (regulation 6). The client notifies HSE.

Does the plan need to be reviewed?

Yes. The principal contractor must make sure it is regularly reviewed, updated and revised throughout the project (regulation 12(4)).

Does CDM apply in Northern Ireland?

CDM 2015 applies in Great Britain. Northern Ireland has the Construction (Design and Management) Regulations (Northern Ireland) 2016, which also expect contractors to prepare a plan. See HSENI for details.

Sources

Sources last checked 27 October 2026. This page has not yet been reviewed by an external health and safety adviser.

This page describes the law in Great Britain (England, Scotland and Wales). Northern Ireland has its own regulations: see HSENI. Kompliant drafts documents for your competent person to review, edit and approve. The guidance on this page is general information, not legal advice.