RAMS template (UK): what to include, section by section
Last updated 13 November 2026 · Sources last checked 27 October 2026
A RAMS is a risk assessment and method statement for one job, written before the work starts. The risk assessment says what could go wrong and how it will be controlled. The method statement says, step by step, how the work will be done safely. Below is a structure you can copy into your own document, and what each section needs to say.
What a RAMS is, and what the law asks for
"RAMS" is a trade term, not a legal one. The law asks for the parts. Employers must make a "suitable and sufficient" assessment of the risks to their employees, and to other people affected by their work, and must write down the significant findings if they employ five or more people (Management of Health and Safety at Work Regulations 1999, regulation 3).
A method statement describes, in logical order, how a job is to be done safely. HSE describes method statements as widely used on construction work rather than something the law demands for most jobs (HSE, construction administration). Some work has its own written-plan rules: for demolition and dismantling, the arrangements must be recorded in writing before the work begins (CDM 2015, regulation 20). Check the rules for your type of work. Many clients and main contractors ask for a RAMS before work starts, whether or not the law requires one.
The structure to copy
- Job details. Title, site address, client, start, end and review dates, and who is in charge on site.
- Summary. One short paragraph: what the work is, where, and the main risks.
- Risk assessment table. One row per hazard, with columns for the hazard, who could be harmed, the risk before controls, the control measures, and the risk after controls.
- Safety-critical activities. Anything that scores high before controls, or is dangerous by nature (isolating live supplies, hot work, work at height, confined spaces, asbestos). Give each its own short procedure.
- Method statement. Three parts: before the work starts (site arrival, induction, briefing, pre-work checks), how the work is done (numbered steps in order), and after the work is finished (clean-up, handover, sign-out).
- Equipment and PPE. What will be used, and the protective equipment each task needs.
- Legislation and standards. The ones that apply to this job, not a standard list pasted onto every document.
- Emergency arrangements. First aid, fire and serious injury, plus the practical details for this site: assembly point, first aider, site contact and nearest A&E.
- Read and understood. Names, signatures and dates showing that each person doing the work has read the document before starting.
Hazards a RAMS commonly covers
Which of these apply depends on the job. Treat the list as a prompt, not a checklist to copy.
| Hazard | Where it comes up | Legislation |
|---|---|---|
| Work at height | Ladders, tower scaffolds, mobile platforms, roofs | Work at Height Regulations 2005 |
| Electricity | Isolating supplies, testing, existing wiring | Electricity at Work Regulations 1989 |
| Manual handling | Carrying materials and equipment | Manual Handling Operations Regulations 1992 |
| Hazardous substances | Adhesives, sealants, solvents, dust | COSHH Regulations 2002 (see the COSHH assessment guide) |
| Noise | Cutting, drilling, breaking out | Control of Noise at Work Regulations 2005 |
| Asbestos | Older buildings; drilling or disturbing ceilings and walls | Control of Asbestos Regulations 2012 |
| Confined spaces | Voids, tanks, ducts | Confined Spaces Regulations 1997 |
Common mistakes
- Text that could be about any site. If the document never mentions the actual building, access route or equipment, it has not been written for the job.
- Hazards that do not apply. A RAMS that lists confined spaces for a ground-floor light fitting shows the text was pasted in, and buries the hazards that do matter.
- Steps too vague to follow. "Install the equipment" tells nobody how, with what, or who does what.
- Nobody has read it. A RAMS that sits in a folder protects no one. Have each person read it, and record that they did.
- Never updated. The assessment must be reviewed if there is reason to suspect it is no longer valid, or if the work changes significantly (regulation 3(3)).
Draft yours in Kompliant
Describe the job in plain English. Kompliant asks follow-up questions about the job before it drafts, then writes the RAMS using your company profile, so it reads like your own document. It scores each risk before and after controls, writes the method statement in three parts, lists the legislation for the trades on the job, and adds a site arrangements block for the assembly point, first aider, site contact and nearest A&E. You review and edit the draft and approve it, and your team signs by link on their phones, with no account needed to sign.
Kompliant produces a draft for your competent person. You are responsible for checking that it fits the job and the site.
Already have a RAMS? Get it checked →
Example: part of a RAMS drafted in Kompliant
Example. Fictional company and job. Draft, not approved.
Replace ceiling LED panels, first-floor open-plan office
Site: Example Client Ltd, first-floor office, Example House, 1 Example Street, Milton Keynes.
Trade: Electrical · Start: 09 Nov 2026 · End: 13 Nov 2026 · Review by: 16 Nov 2026
Summary
This RAMS covers the replacement of 48 recessed 600 x 600 mm T8 fluorescent ceiling fittings with LED panels in a first-floor open-plan office (approx. 400 m²) at Example Client Ltd, Example House, 1 Example Street, Milton Keynes. The office stays occupied throughout. Works are phased in four zones, with staff moved to another part of the floor while each zone is worked on. Two Example Electrical Ltd electricians will work Monday to Friday, 8:00am to 4:30pm, from podium steps under a 2.7 m suspended tile ceiling. Each zone's lighting circuit is isolated one at a time at the riser cupboard distribution board, locked off and proved dead before work starts. […] It is a first draft and must be reviewed and adopted by a competent person before use.
Risk assessment (4 of 17 rows)
Risk ratings use the 5x5 matrix: Likelihood (1-5) × Impact (1-5).
| Hazard | Who's at risk | Before controls | Control measures | After controls |
|---|---|---|---|---|
| Electric shock or arc from live lighting circuits and fittings (isolation failure, re-energisation) | Electricians, office staff, client staff | 15 (3×5) | Isolate one zone at a time at the riser DB; lock off with own personal padlock and tag; prove dead at the first fitting with a proving unit and approved voltage indicator; riser cupboard kept locked with the key held by the lead electrician; second electrician checks the lock-off at the DB; work on dead circuits only per EWR 1989; competent electricians only. | 5 (1×5) |
| Falls from podium steps (2.7 m ceiling, overhead working, handling fittings) | Electricians, staff nearby | 15 (3×5) | Podium steps checked before use each day (brakes, guardrails, gate, condition); used on flat carpet-tile floor only; zone cleared of desks around work area; second electrician at the foot as spotter; no overreaching; one fitting handled at a time; do not use podium as a transport platform. | 5 (1×5) |
| Falling objects (fittings, tiles, grid components, tools) onto people below | Electricians, staff, visitors | 10 (2×5) | Zone fenced with freestanding barriers and signs; marked staff walking route; nobody enters the zone while overhead work is underway; tools kept in a pouch or tray; tiles stacked flat at floor level, not on the steps. | 4 (1×4) |
| Broken fluorescent tubes (glass cuts, mercury-containing powder and vapour) | Electricians, nearby staff | 12 (3×4) | Fittings lifted out whole with tubes left in; each wrapped in heavy-duty bag and carried flat; nobody breaks tubes on site; taken to a lined skip bag at the van; recycled as fluorescent waste through a licensed carrier. […] | 4 (1×4) |
Not applicable to this job and therefore excluded: refrigerant gases, hot works or brazing, confined spaces, weather exposure and scissor-lift or MEWP operation (podium steps only).
Method statement: before activity commences
- Sign in with the site contact on arrival and brief them on the day's zone, access and timing.
- Review the 2021 asbestos management survey with the site contact and confirm no asbestos in the first-floor ceiling void, tiles or grid. Stop if anything unexpected is found.
- Confirm in writing with the site contact the fire alarm arrangements for any tile holding a detector.
[…]
Works methodology
- Set up the podium steps under the first fitting, apply the brakes and have the second electrician in position at the foot.
- Lift ceiling tiles carefully and slowly, stacking them flat out of walking routes. Do not lift tiles holding smoke detectors unless the fire alarm arrangement is agreed. Do not disturb detectors or emergency lighting.
- Disconnect the existing fluorescent fitting from the dead circuit, noting the wiring arrangement.
[…]
After activity has been completed
- Final HEPA vacuum clean of each zone; remove all packaging and waste.
- Confirm all fittings and waste have gone to the licensed carrier for recycling and keep the waste transfer paperwork.
- Check all new panels, emergency lighting and detectors are in place and undisturbed.
[…]
Site arrangements and emergency information
| Item | Detail |
|---|---|
| Assembly point | Front car park, by the main entrance |
| Site contact | Facilities manager, Example Client Ltd · 01632 960456 |
| First aider on site | Sam Example (FAW), Example Electrical Ltd |
| Welfare / toilets | Kitchen and toilets, first floor |
| Nearest A&E | Milton Keynes University Hospital (2.6 km), Standing Way, Milton Keynes, MK6 5LD |
In an emergency call 999 first. Dial 112 from a mobile if 999 fails.
Questions
Is a RAMS a legal requirement?
The law requires a suitable and sufficient risk assessment, and for employers with five or more employees a written record of the significant findings (regulation 3). "RAMS" as a combined document is not a legal term. HSE describes method statements as widely used on construction work, and some work, such as demolition and dismantling, has its own written-arrangements rule. Many clients ask for a RAMS as a condition of the job.
Who should write and sign off a RAMS?
Someone with enough training, experience or knowledge to judge the risks of that job. Employers must appoint one or more competent people to help them meet their health and safety duties, and the Regulations describe competence as sufficient training and experience or knowledge and other qualities (regulation 7). A self-employed employer, not in a partnership, who has sufficient capability to carry out the measures alone does not have to appoint anyone else (regulation 7(6)).
How long should a RAMS be?
As long as the job needs. The assessment has to be "suitable and sufficient", so a short job with few hazards can be short. A long document that is long because it is generic is a sign it has not been written for the job.
Can I reuse a RAMS for similar jobs?
You can reuse the structure and the parts that really repeat. HSE says a method statement can be reused for repeated similar operations, and should be revised when circumstances change markedly. Check each use against the site, the people and the equipment.
How often should it be reviewed?
Whenever there is reason to suspect it is no longer valid, or the work changes significantly (regulation 3(3)). Put a review date on the front.
Sources
Sources last checked 27 October 2026. This page has not yet been reviewed by an external health and safety adviser.
- Management of Health and Safety at Work Regulations 1999, regulation 3
- Management of Health and Safety at Work Regulations 1999, regulation 7
- HSE: Construction, administration (method statements)
- Construction (Design and Management) Regulations 2015, regulation 20
- Work at Height Regulations 2005
- Electricity at Work Regulations 1989
- Manual Handling Operations Regulations 1992
- Control of Noise at Work Regulations 2005
- Control of Asbestos Regulations 2012
- Confined Spaces Regulations 1997
- Control of Substances Hazardous to Health Regulations 2002, regulation 6
This page describes the law in Great Britain (England, Scotland and Wales). Northern Ireland has its own regulations: see HSENI. Kompliant drafts documents for your competent person to review, edit and approve. The guidance on this page is general information, not legal advice.