Risk assessment and method statement (RAMS): how the two documents fit together
Last updated 13 November 2026 · Sources last checked 27 October 2026
A risk assessment and a method statement answer different questions. The risk assessment asks what could harm someone and what will be done about it. The method statement describes how the job will be done, step by step, with those controls built in. Together they are called a RAMS. The method statement is normally built from the risk assessment, so if the two do not match, one of them needs fixing.
The risk assessment: the legal part
Employers must make a "suitable and sufficient" assessment of the risks to their employees at work, and to other people affected by the work, and identify the measures needed to meet their health and safety duties. The same duty applies to some self-employed people (Management of Health and Safety at Work Regulations 1999, regulation 3).
Three further points from regulation 3:
- It must be reviewed if there is reason to suspect it is no longer valid, or if there has been a significant change in what it covers.
- An employer with five or more employees must record the significant findings, and any group of employees identified as being especially at risk.
- Special rules apply before employing a young person (under 18).
HSE's minimum steps are to identify the hazards, assess the risk, and act on it by removing the hazard or controlling the risk (HSE, risk assessment).
The method statement: the practical part
The method statement sets out how the work will be done, in order, with the controls from the risk assessment applied at each step. HSE says method statements are usually produced from risk assessments and bring together the hazards and controls for a specific job. They are widely used on construction work, though for most jobs the law does not require one by name. Some work has its own written-plan rules; for example, for demolition and dismantling the arrangements must be recorded in writing before work starts (HSE; CDM 2015, regulation 20). See the method statement template for how to write one.
Scoring risk before and after controls
Many RAMS score each hazard twice: once before controls, once after. The scores show what you judged the risk to be and how far your controls reduce it.
A common method is a 5×5 grid. Score the likelihood of harm from 1 to 5 and the impact from 1 to 5, and multiply to give a score from 1 to 25. Kompliant uses these bands:
| Score | Band |
|---|---|
| 1 to 4 | Low |
| 5 to 9 | Low to medium |
| 10 to 14 | Medium |
| 15 to 19 | Medium to high |
| 20 to 25 | High |
Regulation 3 asks for a "suitable and sufficient" assessment. It does not set out a scoring method, so a 5×5 grid is one common way to show your judgement, not a rule.
A worked score. From the example below: falls from podium steps while replacing ceiling panels. Before controls, likelihood 3 × impact 5 = 15 (medium to high). After controls (steps checked before use each day, the zone cleared, a second person at the foot, no overreaching), likelihood 1 × impact 5 = 5 (low to medium). The controls bring down how likely a fall is; the harm if one happens is still scored as serious. The scores for your job are for your competent person to decide.
From hazard to step
Each significant hazard should lead to a control, and each control should appear in a step of the method statement.
| Hazard | Control | Where it shows up in the method statement |
|---|---|---|
| Live electrical supply | Isolate, lock off and prove dead before work starts | Pre-start check, then a stop point before the first step that touches the circuit |
| Falls from height | Suitable access equipment, inspected before use | Pre-start equipment check, then named in each step that needs it |
| Dust from drilling | Extraction on the tool, area cleaned after | The drilling step, and the after-work clean-up |
A two-way check
- Does every significant hazard in the assessment have a control that appears in a step?
- Does every control mentioned in a step trace back to a hazard in the assessment?
- When the job changes, have both documents been updated? Regulation 3(3) requires the assessment to be reviewed when the work changes significantly.
Other names
In the UK you will also see "safe system of work", a phrase used in section 2 of the Health and Safety at Work etc. Act 1974. "SWMS" (safe work method statement) is usually the Australian term for a similar document.
Draft yours in Kompliant
Kompliant drafts both halves together, so the hazards and the steps line up. It scores each risk before and after controls on the 5×5 grid, gives anything dangerous by nature its own safety-critical procedure, and writes the method statement from the same job description. You review and edit the draft, approve it, and your team signs by link. It is a draft for your competent person to check against the real job.
Already have a RAMS? Get it checked →
Example: two hazards traced into the method statement
Example. Fictional company and job.
Job: replace 48 ceiling fittings with LED panels in an occupied first-floor office, two electricians, four zones.
| Risk assessment says | Method statement says |
|---|---|
| Electric shock or arc from live lighting circuits and fittings. Before: 15 (3×5). Control: "Isolate one zone at a time at the riser DB; lock off with own personal padlock and tag; prove dead at the first fitting… work on dead circuits only per EWR 1989…" After: 5 (1×5). | Before activity commences, step 7: "Isolate, lock off, tag and prove dead the zone circuit per Safety-critical element A." Works methodology, step 3: "Disconnect the existing fluorescent fitting from the dead circuit…" Safety-critical element A, step 7: "No work on live conductors. If a circuit cannot be proved dead, stop and report to the lead electrician." |
| Falls from podium steps. Before: 15 (3×5). Control: "Podium steps checked before use each day (brakes, guardrails, gate, condition)… second electrician at the foot as spotter; no overreaching…" After: 5 (1×5). | Before activity commences, step 5: "Check the podium steps, tools, test equipment, PPE, lock-off kit and first aid kit." Works methodology, step 1: "Set up the podium steps under the first fitting, apply the brakes and have the second electrician in position at the foot." Step 7: "Repeat for each fitting in the zone, moving the podium steps rather than overreaching." |
Questions
Is a RAMS the same as a risk assessment?
No. A RAMS is a risk assessment and a method statement together. The risk assessment is the legal requirement; the method statement is the practical plan that applies its controls to a specific job.
Do I need a RAMS if I am self-employed?
The legal duty to assess risk falls on employers and on some self-employed people (regulation 3(2)). Whatever the legal position, a client or main contractor may ask for a RAMS as a condition of the work. HSE's pages explain whether health and safety law applies to you.
Do I have to use a 5×5 matrix?
No. The Regulations ask for a suitable and sufficient assessment and do not prescribe a scoring method. A 5×5 grid is a common, easy-to-explain way of showing your judgement.
Who should sign it?
Someone competent should review and approve it, and the people doing the work should read it before starting. Many firms record this with names, signatures and dates.
How often should it be reviewed?
When there is reason to suspect it is no longer valid, or the work changes significantly (regulation 3(3)). Put a review date on the front of each document.
Sources
Sources last checked 27 October 2026. This page has not yet been reviewed by an external health and safety adviser.
- Management of Health and Safety at Work Regulations 1999, regulation 3
- HSE: Risk assessment
- HSE: Construction, administration (method statements)
- Construction (Design and Management) Regulations 2015, regulation 20
- Health and Safety at Work etc. Act 1974, section 2
The 5×5 bands are Kompliant's own scoring, not a legal or HSE standard.
This page describes the law in Great Britain (England, Scotland and Wales). Northern Ireland has its own regulations: see HSENI. Kompliant drafts documents for your competent person to review, edit and approve. The guidance on this page is general information, not legal advice.