Permit to work template (UK): what a permit should contain
Last updated 16 November 2026 · Sources last checked 16 November 2026
A permit to work is a formal written system for higher-risk jobs. HSE describes it as stating exactly what work is to be done and when, with the people doing the work signing to confirm they understand the risks. It turns the risk assessment into controls on the day: who may work, where, when, with which precautions in place, and who has authorised it. A permit does not make a job safe on its own; it is only as good as the risk assessment and the checks behind it.
When you need one
HSE gives these as typical jobs that need a permit to work (HSE, permit to work systems):
- Hot work, such as welding, grinding and cutting.
- Entry into vessels and confined spaces.
- Cutting into pipework carrying hazardous substances.
- Work that needs electrical or mechanical isolation.
HSE also says permits help co-ordinate different jobs so they don't conflict, for example two contractors working on the same system. HSE's guide to managing contractors adds that permits are for high-hazard or unusual jobs where normal safeguards may not be enough, and that contractors should not start such work without a permit or confirmation that one isn't needed (HSG159).
Many site owners also use permits for roof access, work at height over occupied areas, out-of-hours working and anything that needs a fire alarm zone isolated.
What a permit should contain
HSE says a permit should contain all relevant information, be correct and be in a usable format; a single-sided A4 permit may be enough. A permit typically covers:
- Reference and type. A unique number, and the type of permit (hot work, electrical isolation, confined space, work at height, general).
- The work. What is to be done, the exact location on site, and the equipment involved.
- When. Start and finish date and time. A permit is valid only for the period stated.
- Who. The contractor and the named people doing the work, with the person in charge.
- Hazards. The hazards of the job and of the location (asbestos, live services, fragile roofs, occupied areas).
- Precautions. The controls that must be in place before work starts: isolations with lock-off, gas testing, fire watch and extinguishers, barriers, PPE. Each one confirmed.
- Linked documents. The RAMS, any isolation certificate, and other permits that affect the same area or system.
- Authorisation. The name of the person issuing the permit, and the time.
- Acceptance. The person in charge of the work signs to confirm they understand the hazards and precautions.
- Hand-back and close-out. Confirmation that the work is finished, people and equipment are clear, the area is safe, and any isolation can be removed; signed by the contractor and the issuer.
Issuing, handing over and closing
- Check before you sign. The issuer confirms the precautions are actually in place, not just listed.
- Brief the people doing the work. HSE describes the permit as communication between site management, supervisors and the people doing the work.
- Display live permits. HSE says related permits should be linked and displayed so people can see what is isolated or under maintenance.
- Shift changes. If work can't be finished in one shift, it must be left in a safe state with clear instructions for the next shift.
- Hand-back. HSE says the system should have a process for handing plant back on completion. Don't remove isolations or reopen an area until the permit is closed.
Common mistakes
- The permit is treated as the safety measure. HSE is clear that a permit is not a substitute for a robust risk assessment.
- Generic permits. The same wording every time, so nobody reads it.
- Precautions ticked, not checked.
- Permits never closed. The area or system stays "under permit" for weeks, and nobody knows whether it is safe.
- Too many permits at the start of a shift. HSE flags permit overload; plan the work or add authorisers.
HSE's detailed guide, Guidance on permit-to-work systems (HSG250), is free to download. It was written for the petroleum and chemical industries, but its principles apply widely (HSE, HSG250).
How Kompliant Estates handles this
In Kompliant Estates, each work request becomes a numbered permit (PTW-0001 onwards). You choose the permit types when you raise the job; the contractor sends back their RAMS and names who is coming; Kompliant checks that the RAMS plans and controls each permit type you asked for; and the permit can't be issued until every named operative has passed your site induction, unless your reviewer records a reason. The live permit is on the contractor's phone to show on site, and they close it out with notes and photos. Kompliant Estates is in early access.
Questions
Is a permit to work a legal requirement?
HSE's guidance describes permits as the way to control higher-risk jobs such as hot work, confined space entry and work needing isolation, and HSE's guide to managing contractors says such work should not start without one. Check the specific rules for the activity. Whatever the strict position, a written permit is how you show the work was authorised and the precautions were in place.
Who should issue a permit?
A competent person with the authority to stop work, who knows the site and the risks: usually a facilities or estates manager, or a nominated authoriser. HSE says it should be clear who is in charge and who does what.
How long is a permit valid?
Only for the period and the work written on it. If the work, location or people change, issue a new one. If work runs over a shift, hand it over properly or leave the work in a safe state.
Is a permit the same as a RAMS?
No. The RAMS is the contractor's plan for doing the work safely. The permit is your authorisation for that work, at that place and time, once the precautions are confirmed in place.
Can permits be electronic?
Yes. HSE notes that moving from paper to electronic permits brings its own risks, so plan the change and train everyone on the process, not just the software.
Sources
Sources last checked 16 November 2026. This page has not yet been reviewed by an external health and safety adviser.
- HSE: Permit to work systems
- HSE: HSG250 Guidance on permit-to-work systems
- HSE: HSG159 Managing contractors
This page describes the law in Great Britain (England, Scotland and Wales). Northern Ireland has its own regulations: see HSENI. Kompliant drafts documents for your competent person to review, edit and approve. The guidance on this page is general information, not legal advice.